Budgets · 14 January 2026 · 7 min read

What Does a Retail Fit-Out Cost in the UK?

Quick answer: a UK retail fit-out typically costs £40,000 to £90,000 for a small independent shop (50 to 100 sqm) and £90,000 to £250,000 for a mid-size shopping-centre unit (100 to 250 sqm). Bespoke kiosks start from £45,000 plus VAT as a guide, installed, excluding design fees. Cat B office fit-outs run £700 to £1,400 per sqm. The final figure is driven by mechanical and electrical works, landlord requirements, materials and programme.

Nobody publishes fit-out prices, which is exactly why the first quote you receive feels impossible to judge. Here is how we price work, what the ranges usually look like, and where budgets quietly disappear.

The honest ranges

Every unit is different, but after 510+ projects the ranges below are where most UK retail work lands. They assume a shell or a stripped-back existing unit, VAT excluded, and a design-and-build route where one contractor carries the whole job.

Project typeSizeTypical budget
Small independent shop refit50 to 100 sqm£40,000 to £90,000
Mid-size shopping-centre unit100 to 250 sqm£90,000 to £250,000
Bespoke retail kiosk (mall standard)Single unitFrom £45,000 plus VAT as a guide, installed, excluding design fees
Cat B office fit-outPer sqm£700 to £1,400 per sqm
Hospitality and leisureVariesWidest range, driven by kitchens, services and acoustics
Partitions and services being built out before finishes on a fit-out
Every layer has a cost, the visible finish is only the top of the stack.

The five things that actually move the number

Most of the variance between two quotes is not joinery, it is what sits behind the joinery.

  • Mechanical and electrical: new distribution, air conditioning and sprinkler alterations are frequently a quarter of the job
  • Landlord requirements: centre specifications, hoarding, out-of-hours working and management fees
  • Materials: solid surface, stone, veneer and specialist finishes carry very different lead times and prices
  • Programme: a compressed programme means night shifts, and night shifts cost more
  • Condition of the unit: dilapidations, asbestos surveys and floor levelling are the classic unbudgeted items
Known Source retail floor at Westfield Stratford with cork-clad column and hanging rails
Material choices like cork, stone or solid surface move the budget more than people expect.

Where budgets are usually wasted

The two most expensive things in a fit-out are changing your mind late and appointing separate designers, joiners and contractors who each price defensively against one another.

A design-and-build route removes the gap between the drawing and the buildable detail. Because we design, manufacture and install in-house, the person quoting the counter is the person who has to make it fit, which is why our variations tend to be small.

OLLYWOOD team reviewing material samples and drawings in the Cardiff workshop
Early material decisions, made where the work is built, save the most money.

How to get a quote you can actually compare

Ask every contractor to price the same scope and to break the number into design, manufacture, site works, M&E, and management. If one quote is dramatically cheaper, it is almost always missing a line rather than beating the market.

  • Provide a floor plan, photos, and your landlord's fit-out guide
  • State your trading date, not your ideal date
  • Ask what is excluded, that list is more revealing than the total
  • Agree how variations will be priced before work starts
OLLYWOOD bespoke joinery project in progress
A quote that matches the buildable detail is worth more than a low headline number.

Project gallery

Ben's Cookies retail kiosk at Westfield
Retail kiosk
Naski ski shop retail floor in Cardiff
Full retail unit
Vibes cafe counter
Hospitality counter
Viro offices open plan fit-out in Cardiff
Office fit-out

Send us your plan and trading date and we'll come back with a broken-down budget, not a guess.